Yesterday my colleagues at Cosford learned that they had a won a long campaign to stop the privatisation of Defence Training.

In a ministerial announcement it was revealed that it had become necessary to terminate the DTR procurement and Metrix’s appointment as Preferred Bidder because an affordable solution was not forthcoming within the time frame required:

DTR PACKAGE 1 – Collapses.

Introduction

Among all the defence announcements, some of which seem to border upon the insane, is the welcome news that DTR has finally collapsed.

This programme has been limping along for some time, but today the final wheel fell off the wagon.

IPT communicates

Paula Payne from the IPT wrote to MODCSU today. In her letter she noted:

“…you will also be familiar with the challenges with which the project has had to contend:  the separation of Package 1 from Package 2, the withdrawal of Land Securities Trillium as a sponsor of Metrix and the impact of the financial crisis on the costs of funding the project have all been major issues.  They have manifested themselves in an ongoing battle to develop the complex commercial deal within the time required and to make the project affordable.  It has been clear from the outset that this project would only proceed if it was commercially viable, affordable and value for money and Metrix were appointed as Preferred Bidder for DTR in January 2007 subject to these latter two requirements.”

The Ministerial announcement was more forthright in its language:

“The Metrix consortium was appointed as Preferred Bidder in January 2007 subject to it developing an affordable and value for money contract proposal.  Given the significance of this project and the opportunity to provide a world-class training facility, the Ministry of Defence has worked tirelessly to deliver this project.  However, it is now clear that Metrix cannot deliver an affordable, commercially robust proposal within the prescribed period and it has therefore been necessary to terminate the DTR procurement and Metrix’s appointment as Preferred Bidder.”

Metrix heads for the door

Around the Establishments Metrix Liaison Officers are packing their bags and heading out. This is a serious blow to QinetiQ especially, given their dire financial position.

PCS success

Nevertheless, this is a victory for PCS’ strategy of constant engagement with the Department, campaigning and utilisation of information extracted through research and Freedom of Information requests.

The Private Eye carried a constant stream of stories about DTR, provided by PCS, that held the project up to ridicule and PCS worked with local MPs in affected areas, got tabled Parliamentary questions (over 200), lobbied for Early Day Motions, organised Parliamentary drop ins, on line petitions, a 24 hour vigil, supported the Defence Day of Action etc.

MoD has squandered millions of pounds on DTR that could have been spent upgrading training establishments. The privatisation of training was clearly ideologically driven.

What now

We have won a victory but not the war- that much is clear. The IPT will now look at “alternative procurement proposals”, but again the Ministerial announcement makes clear:

“Technical training, collocated on as few sites as possible, remains in our view the best solution for our Armed Forces.  Equally, St Athan was previously chosen as the best location on which to collocate that training for good reasons, and we still hope to base our future defence training solution there.  We will however now carry out some work before finalising the best way ahead; including to confirm both our training and estates requirement, and the best way to structure the solution that will meet them.”

What this means, in reality, is anybody’s guess. However, given the parlous state of MoD finances it is likely that those sites with good infrastructure will remain in situ. The likelihood of a DTC at St Athan looks increasingly untenable, although some HQ function for a virtual DTC is of course a possibility.

The MoD will also have to grapple with the contracts that are coming to an end at Arborfield, Bordon and within the VT Flagship contract with Navy training. These training contracts have been left to wither on the vine as the fell within the scope of DTR- similarly a huge question mark must now sit above the TESC contract to deliver garrison support at Arborfield and Bordon.

The issue of Early Training Transformation will also need close attention. Metrix were given a substantial sum to rationalise training courses. PCS challenged the use of ETT last year- given the uncertainty of the project even then. MoD advised the unions that this work would be utilised even if the project did not go ahead. PCS will be seeking information on just how much of this material is still relevant following the Ministerial announcement.

PCS will also be pressing the DTR IPT for answers on all the above issues at our meeting schedule for November.

Conclusion

Whilst this news is obviously welcome, members need to be aware that other proposals released today by MoD will undoubtedly indirectly have an impact upon training and Instructional Officers and those providing admin support.

Members need to stand together as Civil Servants to protect the services to the front line and to their communities and the public.

Paul Bemrose

Negotiations Officer

The news was covered extensively in Shropshire and Wales, the following links are an example of the reports:

6 Comments CherryPie on Oct 20th 2010

6 Responses to “Defence Training Review Collapses”

  1. Chrissy says:

    Good news for them but pretty dire for the rest of the region :(

  2. jameshigham says:

    Well, that was a victory then.

  3. Richard says:

    Also great news for those of us fighting for the future of the green fields around our village that an MoD led consortium would bury under 3,500 houses were Arborfield to close. Just the confusion and delay as a result of the Metrix deal being terminated was enough to get the local council to defer a decision on going ahead with the plan that was supposed to be made tonight.